"This canal was extremely helpful as we were able to bypass after that spill," Matt Brown, DC Water's interim CEO, told WUSA9 during a walkthrough of the cleanup. The canal he was describing is the Potomac stretch of the C&O, and the work zones at Lock 10, Cabin John and Pennyfield Lock all trace back to the same pipe, the Potomac Interceptor. That line has been under repair since January, and most of the work is now scheduled to wrap up between December and February.
As walking weather turns colder in mid-November, the towpath from Lock 10 to Rileys Lock is open almost the whole way. The Billy Goat Trail is open in all three sections. The bottleneck this winter is parking, with the Swains Lock lot closed and crews taking up part of the lots at Carderock and Pennyfield.
One pipe behind most of the work
The Potomac Interceptor is a 54-mile sewer line. It carries an average of up to 60 million gallons of wastewater a day, from as far away as Dulles Airport, to the Blue Plains treatment plant in Southwest DC. On January 19, 2026, a section of it collapsed along Clara Barton Parkway, and the overflow ran into the C&O Canal National Historical Park.
DC Water built a bypass within five days, pumping wastewater through the canal itself and back into the sewer system downstream. According to DC Water's account of the collapse, the last overflow to reach the Potomac River was on February 8. Emergency repairs were finished March 14, and the canal was then drained so the cleanup could begin.
That cleanup has been big. WUSA9 reported that crews removed nearly 8,500 tons of contaminated topsoil from the canal floor over the spring and summer and are now laying 2,500 tons of replacement clay. That's the last structural step before ground cover, vegetation and water return. DC Water expects full remediation of the site to be finished by December. In October, DC Water said its additional testing showed the Potomac River had returned to normal.
The collapse also set off the rest of this year's work. After January, DC Water inspected the full interceptor with video, LiDAR and sonar. Brown told WUSA9 the utility found four locations needing emergency repair: two near Dulles, one near the District line, and one at Pennyfield Lock. The Pennyfield repair is the one in Potomac.
Each access point as winter starts
Here is the stretch from downstream to upstream. Statuses come from the National Park Service's current conditions page, last updated November 5, 2026.
| Access point | Mile | Status this month | Expected finish |
|---|---|---|---|
| Lock 10 | 8.8 | Lot and towpath open; short towpath delays as equipment moves | Pipe work through February 2027 |
| Carderock | 10.5 | Alternating one-lane traffic in the tunnel; Lot 1 at reduced capacity; restrooms closed, portable toilets open | Lane closure still listed |
| Great Falls Tavern | 14.3 | Entrance road, lot, restrooms, overlook, Olmsted Island boardwalk, Gold Mine Loop and River Trail open | No closures listed |
| Billy Goat Trail | 13.8 | Sections A, B and C open | No closures listed |
| Swains Lock | 16.7 | Lot closed since October 13; hiker-biker campground open | NPS work runs in phases through 2026 |
| Pennyfield Lock 22 | 19.6 | Repair work; possible delays on Pennyfield Lock Road | Work in December, site restoration in January |
| Rileys Lock / Seneca Aqueduct | 22.8 | Aqueduct and lot open | No closures listed |
Lock 10 and Cabin John
DC Water says emergency repairs here were finished in March and construction has moved on to long-term rehabilitation. DC Water is rebuilding a 2,700-foot section between the I-495 interchange and Lock 10. That section includes the stretch near Rock Run that failed in January and released more than 243 million gallons of sewer overflow. Crews are slip lining both the 72-inch and 66-inch pipe sections, which means installing a new pipe inside the old one while bypass pumps carry flow around the work. Construction is expected to continue through February 2027. The Park Service lists the Lock 10 lot and towpath as open, with flaggers moving visitors past equipment. Its conditions page also still carries a DC Water sewer overflow alert for Lock 10 and says visitors there may notice odors.
Carderock
The Carderock project has nothing to do with the sewer line. It's a separate National Park Service tunnel repair addressing erosion and deteriorated concrete, with work on wingwalls, asphalt approaches and signage. Traffic through the tunnel has alternated in one lane since July 27. Contractor staging takes up part of Parking Lot 1, and the restrooms are closed for emergency repairs. The Carderock Pavilion and the other lots are open.
Swains Lock
The Swains Lock closure also has nothing to do with this year's sewer work. The Park Service is repairing damage from the July 8, 2019 flash flood, which eroded embankments along the Great Falls entrance road and damaged the timber retaining wall at the Swains Lock lot. The project page lists rockery armoring, shoulder reconstruction, drainage work and stream-bed stabilization, done in weather-dependent phases through 2026. The lot has been closed since October 13. The entrance road to Great Falls is open.
Pennyfield Lock
At Pennyfield Lock, DC Water is rehabilitating about 1,700 feet of 60-inch pipe near Muddy Branch. On a typical dry day, that pipe carries about six million gallons of wastewater from upstream of important drinking water intakes on the river. DC Water's page says there is no emergency, overflow or drinking-water impact at the site. At an October 7 meeting with the Tobytown community, DC Water said it now expects to finish the work in December and restore the area in January, depending on weather. Crews work 7 a.m. to 5 p.m. and use space in the Pennyfield lot for equipment staging. The Park Service's project summary says parking and visitor access at Pennyfield Lock and Lockhouse 22 are to stay open.
What changes on a winter visit
With the work zones mostly at the lots, a winter outing comes down to where you park and when. The canal also goes through its own winter shutdown, separate from the construction.
The water is mostly gone. The Park Service drains the canal every fall to protect the stonework from freezing, and it's usually refilled in early spring. As of November 5, every managed stretch between Locks 17 and 23 was dry. Widewater was still holding water.
Some faucets go off. Well faucets in camping areas usually shut off around November 15 so the pipes don't freeze. The Swains hiker-biker and Seneca/Rileys faucets are already listed as off. Faucets at Lock 10, Carderock, Anglers, the Great Falls Tavern restrooms and the Swains Lockhouse are listed as on.
The Tavern has shorter hours. The Great Falls Tavern Visitor Center is open Sunday and Wednesday through Saturday, 9 a.m. to 4 p.m., through November. From December 1 through February 28, it's open Sunday and Thursday through Saturday, 9 a.m. to 4 p.m., and closed Monday through Wednesday. The boat rides are done for the season.
Billy Goat Section A depends on the river. The trail usually closes when the Little Falls gauge reaches 5 feet and reopens once it falls to 4.8 feet. The Great Falls Tavern Visitor Center, at 301-739-4200, has the latest closure information during business hours.
On the calendar through mid-December
Two organized ways to use the canal fall within the next five weeks, and both are at the far ends of the Potomac stretch, away from the work zones.
- Guided Tours of Riley's Lockhouse. These Park Service tours start at 1 p.m. on November 15, 21, 22, 28 and 29, and December 5, 6 and 12. The park calendar notes that programs depend on staffing and weather, so check it before you go.
- C&O Canal Association Continuing Hike. On Sunday, December 13, from 11 a.m. to 3 p.m., this roughly five-mile round trip follows the Great Falls Overlook Trail to the crossover at Old Angler's Inn, then returns up the canal to view the falls. Sign up by emailing [email protected], as listed on the Association's event page.
The December dates line up with the repair schedule. DC Water expects the canal remediation near Cabin John to finish by December and the Pennyfield repairs to wrap up that same month, with Pennyfield's site restoration following in January. The Lock 10 pipe work is scheduled to run through February. Before each visit, the NPS conditions page has the current lot and trail status.
The canal is one of the things that makes a home near River Road feel connected to something larger, and that's part of what I talk through with clients when we look at homes between Cabin John and Seneca. If you'd like a sense of how the towpath fits into daily life in different parts of Potomac, Mandana Tavakoli would be glad to walk through it with you. Let's Connect.